Basseterre, St. Kitts, August 6, 2021 (SKNIS): Director of the Public Works Department (PWD), George Gilbert, said that phase three of the Joseph N. France General Hospital will address drainage issues at the northwestern end of the hospital.
In an interview conducted on August 4 with SKNIS, Mr. Gilbert said that the heavy rainfall on 4th August led to flooding on the corridors at the northwestern end of the hospital.
“We apologize for the inconvenience which was caused on August 4, and we assure you that as part of phase three and the roof rehabilitation, which is in progress, that that will help to eliminate most of the problems which we are experiencing.”
He added, “Currently, we have a contractor on site who is doing some work on the roof in the area, however, the work has been slow to progress due to the COVID-19 virus and the logistics in terms of performing the work.”
Director Gilbert also stated that there was a tender for the architectural services for phase three of the hospital and the winner was Design Collaborative in Barbados.
“We will continue to monitor the hospital in the event of heavy rain or storm approaching and see what we can do to mitigate the flooding in the various areas,” he added. -30-
Tuesday, March 10
Trending
- Staff Vacancies within the Caribbean Community Secretariat, Guyana
- Vacancy: SENIOR PROJECT OFFICER – CUSTOMS, Caribbean Community Secretariat
- SAINT KITTS AND NEVIS SALUTES EXCEPTIONAL WOMEN AT INTERNATIONAL WOMEN’S DAY CEREMONY
- The National Commission of St. Kitts and Nevis for UNESCO: 2025, A Remarkable Year in Review
- Saint Kitts and Nevis and Romania Lead Key UN Deliberation Ahead of Selection of Next Secretary-General
- Sasha Lloyd Becomes First National of Saint Kitts and Nevis Selected for Italy–AOSIS Fellowship at the United Nations
- SOLIDARITY IN ACCRA: SAINT KITTS AND NEVIS’ PRIME MINISTER HONOURED AS SPECIAL GUEST AT GHANA’S 69TH INDEPENDENCE ANNIVERSARY
- PRIME MINISTER DREW VISITS CAPE COAST CASTLE, REFLECTS ON SHARED HISTORY